2026
4,600 boxes
Range 3,700 – 5,500
≈ 1.50 GW at 325 kW/box (1,500 MW ÷ 0.325 MW = 4,615)
Independent estimate · mill-cut · 12 Sep 2026
A “Bloom box” here is one Energy Server cabinet — the commercial building block Bloom sells, not a fuel-cell stack and not a whole energy farm. New production is treated as the current 325 kW Energy Server (five ~65 kW power modules). Years are calendar 2026, 2027, and 2028. The numbers are factory output the plants can physically build, not last year’s product acceptances rolled forward.
4,600 boxes
Range 3,700 – 5,500
≈ 1.50 GW at 325 kW/box (1,500 MW ÷ 0.325 MW = 4,615)
6,800 boxes
Range 5,500 – 8,000
≈ 2.20 GW at 325 kW/box (2,200 MW ÷ 0.325 MW = 6,769)
8,600 boxes
Range 6,800 – 10,800
≈ 2.80 GW at 325 kW/box (2,800 MW ÷ 0.325 MW = 8,615)
Forecast units are reconcilable from MW by dividing annual factory MW by 0.325 MW (325 kW) per box. That is the current commercial Energy Server Bloom shows in investor decks and the 2025 product brochure: ~65 kW power module × 5 = 325 kW Energy Server; ten servers make a 3.25 MW “power block.”
Worked conversion used on this page: boxes = MW shipped ÷ 0.325. Example: 1,500 MW in 2026 → 4,615 boxes.
The three yearly box counts on this page are factory production (nameplate × utilization at Fremont / Copy Exactly lines). They are not last year’s product acceptances grown by a percentage. Bloom’s own filings treat those as different clocks.
Through FY2023 Bloom published a key operating metric: product accepted — “the number of customer acceptances of our Energy Servers in any period. We recognize revenue when an acceptance is achieved.” Each server was counted in 100 kW equivalents. FY2023 10-K table:
| Year | Product accepted (100 kW eq.) | MW accepted, net | Product revenue |
|---|---|---|---|
| 2022 | 2,281 | 228 MW | $881 million |
| 2023 | 2,682 (+17.6%) | 268 MW | $975 million |
Acceptance is not the factory gate. The 10-K says control (and therefore product revenue) transfers at customer acceptance, which depending on the contract is (1) shipped and delivered, (2) mechanical completion, or (3) commencement of operations (power on). Installation is a separate line, often later, percent-complete. The FY2024 10-K then stopped reporting product-accepted kW because solutions (islanded microgrids, BOP) made a simple kW count “no longer as relevant.” CFO on the Q4 2024 call: in earlier years “timing of product revenue recognition was somewhat divorced from timing of product shipments”; now product revenue is “primarily recognized on shipments,” but still not on factory completion.
2025 product revenue was $1.531 billion (FY2025 10-K). At ~$3.0–$3.4/W that is roughly 450–510 MW accepted, or about 1,400–1,570 current 325 kW boxes. Rolling that forward at 20–40% would give ~1,700–2,200 boxes in 2026 — far below the factory forecast. We do not do that.
Factory constraint is the other clock: management said ~1 GW/year now, 2 GW/year by end of 2026. A 1.5 GW produced year is ~4,600 boxes at 325 kW. Q2 2026 product revenue of $935M already implies an acceptance run-rate that only exists if Fremont is building well above 2025 accepted MW. Channel lag can still leave factory MW ahead of accepted MW (finished goods, SK timing, site readiness) or, in a catch-up quarter, behind it.
| 2025 (actual, accepted) | 2026 (this page: produced) | 2027 (produced) | 2028 (produced) | |
|---|---|---|---|---|
| MW | ~0.45–0.51 GW accepted | 1.50 GW factory | 2.20 GW factory | 2.80 GW factory |
| Boxes @ 325 kW | ~1,400–1,570 accepted | 4,600 produced | 6,800 produced | 8,600 produced |
Assumption used in the three yearly numbers: production can exceed acceptances by ~0–30% in a ramp year (inventory + delayed sites). 2026 factory 1.50 GW vs ~1.0–1.2 GW implied by the $3.9–$4.2B revenue guide’s product slice is that lag, not a second count of the same boxes.
Bloom’s disclosed nameplate is annual production capacity run rate at the Fremont, California cell-print plant (164,000 sq ft lease at 44408 Pacific Commons Blvd., grand opening 2022). Stacks printed in Fremont are assembled into Energy Servers at the Newark, Delaware factory (owned 178,000 sq ft plus leased R&O/warehousing) and a Republic of Korea full-assembly plant (SK ecoplant JV). Company filings treat Fremont GW as the bottleneck; Delaware and Korea are Copy Exactly assembly, not a second GW of cells.
| Plant | Role | Nameplate used here | Notes from filings |
|---|---|---|---|
| Fremont, CA (164k sq ft + 89k R&D/mfg) | Cell print / stack capacity (the GW number) | 1 GW/year now; 2 GW/year by end of 2026; site can go to ~5 GW | FY2025 10-K: “expanding our annual production capacity run rate at our Fremont facility from 1 gigawatt to 2 gigawatts … complete … by the end of 2026.” Each extra 1 GW ≈ 6–9 months and $100–$150M. 2022 press: Fremont “annual output of more than one gigawatt.” |
| Newark, DE (owned 178k + leased R&O ~133k) | Energy Server assembly / Copy Exactly | Sized to take Fremont stacks; 25 acres for more lines | FY2025 10-K: “same manufacturing lines … Fremont, California cell print factory and Delaware assembly facility.” Not a separate GW of cells; utilization tracks Fremont stack output. |
| Korea assembly (SK ecoplant JV) | Full assembly for Korea offtake | Local assembly of U.S.-printed stacks; not additive GW | FY2025 10-K: “full-assembly facility in the Republic of Korea.” Offtake ~60–80 MW/year of the factory total, not extra nameplate. |
Bloom does not publish a utilization %. We apply a factory-utilization assumption to Fremont nameplate (Delaware/Korea assemble what Fremont prints). Formula: implied boxes = Fremont nameplate (GW) × utilization × 1,000 MW/GW ÷ 0.325 MW/box.
| Year | Fremont nameplate (annual run-rate, time-weighted) | Utilization used | Implied factory MW | Implied boxes @ 325 kW |
|---|---|---|---|---|
| 2026 | Ramps ~1.0 GW → 2.0 GW YE; mid-year ~1.75 GW run-rate | ~85% of that mid-year run-rate (ramp, staffing, yield) | 1.75 × 0.85 ≈ 1.50 GW (range 1.2–1.8) | 4,600 (3,700–5,500) = 1,500 / 0.325 |
| 2027 | Full-year ~2.0 GW plus ~0.2–0.4 GW Copy Exactly if they add a line | ~90–95% (first full year at 2 GW) | ≈ 2.20 GW (1.8–2.6) | 6,800 (5,500–8,000) = 2,200 / 0.325 |
| 2028 | ~2.6–3.4 GW if they keep adding 1 GW lines “ahead of committed orders” | ~85–95% (new lines start under-utilized) | ≈ 2.80 GW (2.2–3.5) | 8,600 (6,800–10,800) = 2,800 / 0.325 |
Ceiling check: a fully utilized 2 GW Fremont nameplate is 2,000 / 0.325 ≈ 6,150 boxes/year. 2026 sits below that because the 2 GW line is not available all year and we use 85% utilization. 2027–28 exceed 6,150 only if Newark/Fremont Copy Exactly adds more than 2 GW of stacks. Delaware and Korea do not add extra boxes beyond Fremont stack output in this model.
FY2025 10-K: Korea deployed base ~682 MW. PDA with SK eternix runs through 31 Dec 2027. SK ecoplant take-or-pay was at least 500 MW for 2022–2024; December 2023 added 250 MW of purchase commitments through 2027 and stretched remaining original take-or-pay. That 250 MW over 2024–2027 is roughly 60–80 MW/year if even, or ~185–250 boxes/year at 325 kW — a floor in the Korea channel, not the whole factory. U.S. AI / AEP / Oracle volumes dominate 2026–28 output.
If product ASP is about $3.0–$3.4 per watt (2024 product $1.09B; 2025 product ~$1.5B; Q2 2026 product $935M at ~88% of revenue), then:
Not company guidance. Not investment advice. Point estimates will be wrong; ranges are the honest output. If Bloom’s next Energy Server rating moves off 325 kW, divide the same MW by the new kW/box.